below is a summary of the planned outages that could affect capacity or
impact any receipt/delivery locations during the Rover 2026 outage season. This
schedule is not a complete list of all outages and is subject to change as
the season progresses to reflect any project delays, cancellations or
additions. Additionally, anticipated impact and restrictions are subject to
change.
*All scheduled dates represent gas days as defined in the Rover Tariff to
mean a period of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
|
|
Start Date
|
End Date
|
Location
|
Unit(s)
|
Maintenance
|
Anticipated Impact
|
Meter(s) Impact
|
|
1/6/26
|
1/6/26
|
Majorsville
|
201
|
Preventative Maintenance
|
Capacity through
Majorsville station limited.? Meter subject to scheduling reductions.
|
70004
|
|
1/7/26
|
1/7/26
|
Leesville
|
204
|
Preventative Maintenance
|
Mainline capacity may be
limited; IT and Secondary Out of Path nominations are subject to scheduling
reductions
|
All customers Mainline
capacity limited
|
|
1/13/26
|
1/13/26
|
Leesville
|
202
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of
Path nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
|
1/21/26
|
1/21/26
|
Sherwood
|
201
|
Preventative Maintenance
|
Capacity through Sherwood station limited. Meter subject
to scheduling reductions.
|
70001
|
|
1/22/26
|
1/22/26
|
Bulger
|
203
|
Preventative Maintenance
|
Capacity through Bulger station limited. Meter subject to
scheduling reductions.
|
70005
|
|
2/10/26
|
2/13/26
|
Leesville
|
204
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of
Path nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
|
2/24/26
|
2/27/26
|
Leesville
|
203
|
Preventative Maintenance
|
Mainline capacity may be limited; IT and Secondary Out of
Path nominations are subject to scheduling reductions
|
All customers Mainline capacity limited
|
|
4/9/26
|
4/9/26
|
Sherwood
|
Station
|
ESD
|
Capacity through Sherwood station limited. Meter subject
to scheduling reductions.
|
70001
|
|
4/15/26
|
4/15/26
|
Majorsville
|
Station
|
ESD
|
Capacity through Majorsville Station Limited. Meter
subject to scheduling reductions.
|
70004
|
|
5/20/26
|
5/20/26
|
Seneca
|
Station
|
ESD
|
Capacity through Seneca Station Limited. Meters subject
to scheduling reductions.
|
70002, 70016, 70012
|
|
7/29/26
|
7/29/26
|
Clarington
|
Station
|
ESD
|
Capacity through Clarington Station limited. Meter
subject to scheduling reductions.
|
70011
|