Updated as of
|
|
3/5/2026
|
|
|
|
|
|
|
|
|
|
|
|
|
Listed below is a summary of the planned outages that could
affect capacity or impact any receipt/delivery locations during the TGC 2026
outage season. This schedule is not a complete list of all outages and is
subject to change as the season progresses to reflect any project delays,
cancellations or additions. Additionally, anticipated impact and restrictions
are subject to change.
*All scheduled dates represent gas days as defined in the TGC Tariff to mean
a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m.
(Central Clock Time).
|
|
Start Date
|
End Date
|
Location
|
Unit(s)
|
Maintenance
|
Anticipated Impact
|
Meter(s) Impact
|
|
01/06/2026
|
01/06/2026
|
Centerville
|
4724
|
Maintenance
|
Pressure Fluctuations. Capacity
through Centerville station may be limited and subject to scheduling
reductions.
|
None
|
|
01/13/2026
|
01/13/2026
|
Centerville
|
4721
|
Maintenance
|
Pressure Fluctuations.
Capacity through Centerville station may be limited and subject to scheduling
reductions.
|
None
|
|
01/14/2026
|
01/14/2026
|
Centerville
|
4723
|
Maintenance
|
Pressure Fluctuations. Capacity
through Centerville station may be limited and subject to scheduling
reductions.
|
None
|
|
01/19/2026
|
01/20/2026
|
Longville
|
4511
|
Maintenance
|
Capacity through Longville
station may be limited and subject to scheduling reductions.
|
None
|
|
01/21/2026
|
01/21/2026
|
Longville
|
4505
|
Maintenance
|
Capacity through Longville
station may be limited and subject to scheduling reductions.
|
None
|
|
01/21/2026
|
01/21/2026
|
Longville
|
4506
|
Maintenance
|
Capacity through Longville
station may be limited and subject to scheduling reductions.
|
None
|
|
01/22/2026
|
01/22/2026
|
Longville
|
4508
|
Maintenance
|
Capacity through Longville
station may be limited and subject to scheduling reductions.
|
None
|
|
01/22/2026
|
01/22/2026
|
Longville
|
4509
|
Maintenance
|
Capacity through Longville
station may be limited and subject to scheduling reductions.
|
None
|
|
01/28/2026
|
01/29/2026
|
Longville
|
4510
|
Maintenance
|
Capacity through Longville
station may be limited and subject to scheduling reductions.
|
None
|
|
02/02/2026
|
05/01/2026
|
Longville
|
4509
|
Maintenance
|
Capacity through Longville station may be limited and
subject to scheduling reductions.
|
None
|
|
02/10/2026
|
02/10/2026
|
Longville
|
200-3
|
Cleaner tool run
|
Pressure Fluctuations.
|
None
|
|
02/17/2026
|
02/19/2026
|
Kaplan
|
4627 & 4628
|
Maintenance
|
Higher Daily Line
Pressures and Pressure Fluctuations. Capacity through Kaplan station may be
limited and subject to scheduling reductions.
|
None
|
|
02/18/2026
|
02/18/2026
|
Longville
|
4505
|
Maintenance
|
Capacity through Longville
station may be limited and subject to scheduling reductions.
|
None
|
|
02/24/2026
|
02/24/2026
|
Centerville
|
4723
|
Maintenance
|
Pressure Fluctuations. Capacity
through Centerville station may be limited and subject to scheduling
reductions.
|
None
|
|
03/18/2026
|
03/18/2026
|
Longville
|
4505
|
Maintenance
|
Capacity through Longville station may be limited and
subject to scheduling reductions.
|
None
|
|
03/23/2026
|
04/06/2026
|
Upstream of Beeville
|
Integrity Work
|
Pressure Reduction
|
|
|
04/14/2026
|
04/18/2026
|
Kountze
|
Station
|
Vibration Upgrade
|
All forward haul nominations that traverse this Kountze
station (MP -73.7) will be reduced to zero.
|
None
|
|
04/14/2026
|
04/18/2026
|
Longville
|
Station
|
Maintenance
|
Capacity through Longville station may be limited and
subject to scheduling reductions.
|
None
|
|
04/14/2026
|
04/24/2026
|
Kaplan
|
300-1 Line
|
Hydrotest
|
Capacity into ELA will be limited and subject to
scheduling restrictions.
|
All ELA locations and 82708-Florida Vermilion
|
|
04/14/2026
|
04/21/2026
|
Pollock
|
Station
|
Maintenance
|
Pressure Fluctuations. Capacity through Pollock station
may be limited and subject to scheduling reductions.
|
None
|
|
04/14/2026
|
04/14/2026
|
Kaplan
|
Station
|
Isolation ESD
|
Higher Daily Line Pressures and
Pressure Fluctuations. Capacity through Kaplan station may be limited and
subject to scheduling reductions.
|
None
|
|
04/21/2026
|
04/21/2026
|
Longville
|
4501-4509
|
Noise Survey
|
Capacity through Longville
station may be limited and subject to scheduling reductions.
|
None
|
|
04/22/2026
|
04/22/2026
|
Longville
|
4505
|
Maintenance
|
Capacity through Longville station may be limited and
subject to scheduling reductions.
|
None
|
|
05/11/2026
|
06/19/2026
|
Longville
|
4508
|
Maintenance
|
Capacity through Longville station may be limited and
subject to scheduling reductions.
|
None
|
|
05/13/2026
|
05/13/2026
|
Longville
|
4505
|
Maintenance
|
Capacity through Longville station may be limited and
subject to scheduling reductions.
|
None
|
|
06/17/2026
|
06/17/2026
|
Longville
|
4505
|
Maintenance
|
Capacity through Longville station may be limited and
subject to scheduling reductions.
|
None
|
|
06/29/2026
|
09/25/2026
|
Longville
|
4505
|
Maintenance
|
Capacity through Longville station may be limited and
subject to scheduling reductions.
|
None
|
|
07/15/2026
|
07/15/2026
|
Longville
|
4506
|
Maintenance
|
Capacity through Longville station may be limited and
subject to scheduling reductions.
|
None
|
|
07/16/2026
|
07/16/2026
|
Longville
|
4508
|
Maintenance
|
Capacity through Longville station may be limited and
subject to scheduling reductions.
|
None
|
|
07/16/2026
|
07/16/2026
|
Longville
|
4509
|
Maintenance
|
Capacity through Longville station may be limited and
subject to scheduling reductions.
|
None
|